Advertisement

Serious design, construction and maintenance defects doomed Oroville Dam, report says

Share via

Design flaws, construction shortcomings and maintenance errors caused the Oroville Dam spillway to break apart in February, according to an independent analysis by Robert Bea for the Center for Catastrophic Risk Management at UC Berkeley.

Bea, a co-founder of the center and retired civil engineering professor, found that in the 1960s, when the dam was being planned, designers did not call for a thick enough concrete spillway floor. Nor did they require the continuous steel reinforcement needed to keep its slabs intact during decades of service.

For the record:

9:57 p.m. Dec. 21, 2024A previous version of this article referred to the Center for Catastrophic Risk Analysis. Its name is the Center for Catastrophic Risk Management at UC Berkeley.

The design also did not require strong enough anchors into the underlying mountainside to resist movements downhill and from side to side.

Advertisement

The analysis is the first major assessment of what caused the massive damage that forced the evacuation of nearby Oroville and left the state with a repair bill likely to reach into the hundreds of millions of dollars.

It also sends a warning that the state’s aging fleet of dams may contain unknown defects that would threaten public safety in future wet years.

California Department of Water Resources spokeswoman Erin Mellon said the agency has not seen Bea’s analysis.

Advertisement

The Federal Energy Regulatory Commission, which has oversight of the Oroville Dam, ordered the department to conduct an official investigation and last month a panel of six experts appointed by the DWR began work.

“We anticipate that their findings will be of interest to dam owners around the world,” Mellon said. “Their investigation is open-ended, and they have a great deal of complex information to analyze. The forensics team is expected to give DWR a plan and schedule soon.”

Bea, a member of the National Academy of Engineering, was a pioneer in engineering risk analysis during his days as a Shell Oil Co. vice president, overseeing offshore platforms in the Gulf of Mexico. He later helped conduct independent investigations into the New Orleans levee system that failed during Hurricane Katrina in 2005.

Advertisement

Bea’s Oroville analysis is based on original design drawings, which he obtained in the days after the spillway began to break apart, annual inspection reports and photos taken before and after the failure.

After the failure, state and federal regulators clamped tight restrictions on the information, citing national security concerns.

The spillway is a key part of the dam, allowing large discharges of water when the reservoir is nearly full. It began failing on Feb. 7 when dam operators opened gates that sent 55,000 cubic feet of water roaring out of the reservoir after days of continuous rain drenched the Feather River watershed.

The damage occurred at just a fraction of the spillway’s designed capacity of 300,000 cubic feet per second.

A second, higher spillway provides for emergency releases, but until February, operators had never used it..

After runoff damaged the main spillway, they shut it down and sent water flowing over the emergency spillway, but a massive section of mountainside quickly began eroding upward toward a weir that holds back 30 vertical feet of water.

Advertisement

Authorities ordered more than 100,000 people below the dam to evacuate during the crisis. The event forced dam operators to again use the main spillway, which then suffered additional damage.

Bea’s research found that the failure point occurred about a third of the way down the spillway, at an embedded clay drain pipe. .

The slab is 15 inches thick in most places, but the pipe is 6 inches in diameter and the bell housing at the end of the pipe is 10.4 inches in diameter, meaning that over the pipe the slab was just 4 to 6 inches thick — not much better than a common sidewalk, Bea said.

“The spillway failed at its weakest point,” he said.

The drains play an important function in protecting the spillway. Massive amounts of water move through the ground underneath the spillway, exerting tremendous uplifting force, known as hydraulic jacking.

An important factor in the failure was that the drain near the failure point was likely plugged by roots growing from nearby trees and shrubs, based on photos that show no water exiting the drain outlet along the spillway’s vertical wall.

Advertisement

If the drain was plugged, then the spillway was being uplifted by a force of 1,000 pounds per square foot and pounded on the top by raging waters, Bea said.

The failure point also appears to be near a drain line that was repaired in 2013, meaning that the area could have been degrading for years. Bea said the repairs involved patching cracks and fissures with concrete, which provided little strength to resist the forces that it would bear.

“It would disintegrate like potato chips under these hydraulic forces,” Bea said.

But even if the drains were working properly, they would not have prevented the failure, Bea said.

The spillway is constructed in approximately 40 foot sections along its width, but the sections are not tied together with a continuous string of reinforcing steel, according to original design drawings in the Bea report. Only a short steel dowel connects each section, not enough to keep the structure intact under very high forces that would occur when large amounts of water are flowing.

The Bea report shows that the spillway handled 129,000 cubic feet of water per second in the late 1990s, but since then it has been used for relatively minor discharges in most years. The lack of use likely concealed years of deterioration that was weakening the structure, he said.

The DWR website said the agency is assessing a repair and replacement plan to prepare the spillway for action by Nov. 1.

Advertisement

The agency has received bids from three contractors for repairs, ranging from $275 million to $344 million, well above the state’s expectations. Late Monday, DWR said that Kiewit Corp. of Omaha was awarded a $275-million contract to make the repairs.

Since the failure, state and federal officials have taken inspection reports and design documents offline and refused public information requests for their disclosure. Bea said that in his view institutions are attempting to protect themselves from criticism.

The technical problems in the spillway should call into question the adequacy of the dam itself and the adequacy of about 20 other California dams built in the same time period, he said.

“Good risk management would dictate that we should look at all the dams of that era,” Bea said. “This is not an Oroville problem. It is a state problem and a national problem.”

ralph.vartabedian@latimes.com

Follow me on Twitter @rvartabedian

ALSO

Candidate’s endorsement ‘contract’ with a former rival draws complaints in L.A. City Council race

L.A. County seeks to strengthen the safety net for its neediest residents with funding for the homeless, social workers and healthcare

Advertisement

Comedian Katt Williams ordered to complete anger management classes in Beverly Hills robbery case


UPDATES:

10:10 p.m.: This article has been updated with information about a repair contract being awarded to a contractor.

This article was originally published at 7:20 p.m.

Advertisement