Major reconstruction of streets and alleys within the Downtown area

is in progress and will continue through May. Along with the street

work, overhead utilities are being moved under ground and various

sections of sewer lines are being replaced. The combined projects

will have one or two streets affected on a daily basis throughout the

next four months. There will be no work on President’s Day, Monday.

Overhead utilities will be placed under ground on Park Avenue

through the middle of February. The work will involve periodic lane

closures just below Skyline Drive.

Work will continue on Vista Lane and proceed toward Mystic Way.

Work on Mystic Way will begin just below the intersection with

Mystic View and proceed toward Hilledge Drive. Street closures of

about 100 feet in length will move down Mystic Way, approaching

Hilledge drive over the next few weeks.