In addition to the sewer reconstruction work...

Share via

In addition to the sewer reconstruction work and the underground

placement of utility poles already in progress in the Downtown area,

projects planned for next week include work at the intersections of

Beach Street and Ocean Avenue, Forest and Ocean avenues and Forest

and Glenneyre Street. Work is scheduled to continue on the Downtown

rehabilitation project through May.

Sidewalk construction along the inland side of North Coast Highway

from Viejo Street to Ledroit Street is planned. This work will close

the outbound, No. 2 lane from 9 a.m. to 3 p.m. The work will continue

through the month of April.

A road widening project is scheduled in front of 2236 Crestview

Place. The work is expected to cause delays through mid-April.